On February 28 we had our second meeting regarding the project. On this meeting we showed our latest advance on the development of the project´s GUI. The mayor problem for this checkpoint was to get the application to display the "Spinner" options that we wanted, nevertheless we managed to get the spinners working as we wanted.
The following pictures show the application running on the emulator on a hardcoded basis:
We have met with the client to show the advance on the project and the use cases that she originally requested. The client accepted and signed the acceptance requests and was happy with the development of the application.
The next step for the project will be the development of the Data Base and the way it´s going to interact with the application. To do that, we are going to meet with the tutor to have a better understanding of the process.